the beginning, after we help you write your project
brief, we engage on your behalf the building cost consultant
to ensure your expectations are financially realistic.
We require our clients to set a realistic project brief.
Peter
Dalton Architects House Design Budgeting Tool
Preparing
a cost estimate during the design stage BACK
The conceptual design stage may involve evaluating a
number of design options and their associated cost.
Cost estimates at this stage naturally have a degree
of approximation as many detailed aspects of construction
and selection of finishes and fittings are yet to be
resolved. Design development is also subject to review
of the conceptual design with Council planning officers
which may result in changes which can increase costs.
Design development can also modify building costs. Our
building cost consultant keeps you informed of these
adjustments.
(see
example)
Carrying
out a financial feasibility of the development
BACK
Your project may be for future sale or rental. If that
is the case, in association with our building cost consultants
we are able to provide a financial feasibility at the
conceptual design stage which will demonstrate the possible
return on invested funds.
Confirming
the cost estimate prior to lodging the development application
BACK
Development consent locks you into the design unless
you apply for a change to the consent or appeal to the
Land and Environment Court against Councils refusal,
or the conditions it has imposed. Consequently it is
important to confirm that the design which is lodged
with Council is still on budget before the application
is lodged.
Council can also cause increase in costs as a result
of the development consent conditions it imposes at
the time of approving the development application.
(see
example)
Updating the cost estimate at the construction certificate
stage BACK
The construction certificate commits you to build in
accordance with the requirements of the Building Code
of Australia (BCA). These requirements have cost consequences.
We have the Building Cost Consultant confirm the cost
estimates at this stage to ensure that such compliance
is within budget.
(see
example)
Updating the cost estimate prior to calling building
tenders BACK
When you invite builders to tender they expect that
the proprietor (the client) has the financial capacity
to pay for the construction. Our building cost consultant
checks that the detailing, selection of finishes and
fittings are within budget as these are progressively
documented. It is very easy to increase costs when selecting
finishes and fittings, and resolving construction details.
This will be reflected in the tender prices.
We also seek advice from the building cost consultant
about the likely impact of supply and demand amongst
the type of builders who may be suitable for your project
to ascertain the likely tendering environment. Inflation
and market forces can cause tenders to vary from cost
estimates.
Peter
Dalton Architects House Design Budgeting Tool
Checking that tenders are financially realistic BACK
All tenders are selected on the basis that they have
the capability to undertake the type of construction
expected.
Not withstanding this pre-qualification tenders may
vary significantly.
Some builders may, when invited to tender, be busy but
wish not to be excluded because of the prospect of doing
future work with the architect. Others may, during the
tender period sign contracts which fill their work schedule
for the foreseeable future. Some may under-estimate
the difficulty of certain aspects of construction, or
not understand the ease of construction methods. Different
builders will estimate the time for construction differently.
Builders subcontractors may also be subject to
all these factors. Consequently it is not unusual to
have a significant variations in submitted tenders.
Some tenderers may choose not to submit a tender for
all, or any, of the above reasons.
With the building cost consultant we check that tenders
are financially realistic.
Certifying that the builders monthly progress
claims are reasonable BACK
The building contract requires that the builder submit
progress payments. These are usually submitted monthly.
The claim is broken down by trades, and may involve
claims for provisional or prime cost sums for finishes
or fittings. The claim is evaluated by the architect
and the building cost consultant to check that it represents
a reasonable claim for the work carried out in the previous
month. If there are any discrepancies adjustments may
be made to the claim. The reasons for these adjustments
are included in the certificate requiring the proprietor
(the client) to pay.
(see
example)
Ensuring that costing of any variations are reasonable BACK
There can be many reasons for variations. The foundation
conditions may require adjustment to the footings and
may vary from the test bore results produced by the
geotechnical engineer. This may effect excavation and
construction costs. Sub-surface drainage conditions
may vary from that assumed requiring adjustment to the
drainage (nobody can see under the ground). If the project
involves alterations and additions, opening up of existing
construction may reveal unsatisfactory conditions requiring
additional work, and even re-design of details, finishes
and methods of construction. The clients may, after
watching the building come into existence see additional
work that they decide they want done. Selection of finishes
or fittings, which may have been deliberately left until
during construction, will result in adjustments to provisional
or prime cost sums. Wet weather may delay construction.
Strikes, or unforeseeable delays in transport if materials
or products are imported can cause delay.
All of these, and other causes which the contract allows,
can be a reasonable basis for a variation to the contract.
With the building cost consultant we check that any
variation claims are allowed under the contract, and
if so, priced realistically.(see
example)
Ensuring that extension of time claims and any costs
arising are reasonable BACK
Variations and other contractually valid reasons for
delay can be the basis of legitimate extension of time
claims and associated costs, if so defined in the contract.
We determine whether such claims are legitimate, and
in conjunction with the building cost consultant if
the costs claimed are reasonable. (see
example)
Documenting the final construction accounting BACK
At practical completion the final contract accounts
are prepared. These include a statement of payments
made against all the trade breakdowns, adjustments of
provisional and prime cost sums, accounting of all variations
and any costs associated with extensions of time.
At the issuing of the certificate of practical completion
half the retention sum is released. The other half is
retained until the end of the defects liability period
and all defects have been fixed.
Issuance of the final certificate the when all defects
have been properly rectified and the remainder of the
retention is released completes the building contract.
(see
example)
BACK
| Any
or all of the pages of the website may be downloaded
for the information of the viewer, however, all
the content of each page remains copyright to Peter
Dalton Architects. |
|